Compare actual and budgeted results with the same definitions. Separate volume, job mix, price, direct cost, overhead, and timing effects where useful. “Below budget” is the beginning of the investigation, not an explanation.
If a material price changes, update the supported purchasing assumption. If the team completes fewer jobs because access was unavailable, examine the readiness process. Do not label every variance a sales or technician-performance problem.
Keep the original budget and the current forecast distinct. The first records the approved plan; the second incorporates new information. Replacing the original after every change makes it harder to learn which assumptions were unreliable.
For equipment and material inputs, give Mar-Hy the exact scope, quantities, and timing. Use current confirmed information in the budget and cash plan rather than treating an old quote as a permanent future cost.